What's live. What's next.

tectm is the live margin instrument for contractors. The budget, the program and the margin are live today. Here's everything that's running, and the roadmap it's growing into.

01
Live · Your program is a P&L in disguise

Cost-loaded program

A logic-driven CPM schedule that shares your budget's data. Forward and backward pass, FS/SS/FF/SF links with lags, float and the critical path, immutable baselines and slippage, Excel import with a strict validator. Cost-load it and every budget line time-phases into planned value, then the site diary closes the loop and earned-value forecasting does the rest.

  • Forward/backward pass · float · critical path
  • FS/SS/FF/SF + lags
  • Baselines + slippage
  • Excel import (validated)
  • Cost-loaded → planned value
  • EVM: SPI / CPI / EAC
  • Diary closed-loop progress
  • Projected-margin strip

Desktop today; field view on the roadmap

app.tectm.com — Program

LD Recovery Exposure

Counterparty

Apex Civil Pty Ltd

Target

7 Feb 2026

Forecast

25 Feb 2026

Days late

18

ActivityDurCost
1.1Bulk Earthworksoverdue8d$485k
1.2Piling12d$1.2M
1.3Ground Floor Slab6d$620k
1.4Structural Steel Erection18d$2.2M
2.1Suspended Slabs L1–L624d$3.4M
2.2Structure topped out
Feb 26Mar 262/29/216/223/22/39/316/323/3
100%
100%
72%
45%
12%
PVEVAC
PV $8,640,000EV $7,925,000AC $8,180,000
SPI 0.92CPI 0.97Figures illustrative
02
Live

Budget & live margin

Hierarchical budget lines, trade- and cost-type-tagged, five values each. Actuals light up from certified claims and finalised diary cost; the forecast rides on earned-value performance; the margin is revenue earned minus cost incurred, live at every level.

Budgeted

Committed

Actual

Forecast

Variance

app.tectm.com — Budget
WQ

Wentworth Quarter

Aurora Property Group

Revenue Forecast

$22.0M

Cost Forecast

$20.2M

Projected Margin

$1.8M(8.2%)

VS Budget

+$240k

AT Budget

$11,963,310

Draft · Project Budget

Budget lines

01Civil Works
Budgeted
$4,850,000
Committed
$4,720,000
Actual
$3,950,000
Forecast
$4,780,000
Variance
+$70,000
01.01Earthworks & Bulk Excavation
Budgeted
$1,800,000
Committed
$1,760,000
Actual
$1,760,000
Forecast
$1,760,000
Variance
+$40,000
01.02Stormwater & Drainage
Budgeted
$950,000
Committed
$920,000
Actual
$740,000
Forecast
$920,000
Variance
+$30,000
01.03Paving & Kerbing
Budgeted
$680,000
Committed
$660,000
Actual
$410,000
Forecast
$680,000
Variance
$0
01.04Landscaping & Soft Works
Budgeted
$1,420,000
Committed
$1,380,000
Actual
$1,040,000
Forecast
$1,420,000
Variance
$0
02Structural Works
Budgeted
$6,790,000
Committed
$6,900,000
Actual
$5,620,000
Forecast
$6,940,000
Variance
–$150,000
02.01Concrete & Formwork
Budgeted
$3,200,000
Committed
$3,280,000
Actual
$2,800,000
Forecast
$3,280,000
Variance
–$80,000
02.02Structural Steel
Budgeted
$2,390,000
Committed
$2,410,000
Actual
$1,920,000
Forecast
$2,460,000
Variance
–$70,000
02.03Precast Facade Panels
Budgeted
$1,200,000
Committed
$1,210,000
Actual
$900,000
Forecast
$1,200,000
Variance
$0
Total Budget
Budgeted
$11,640,000
Committed
$11,620,000
Actual
$9,570,000
Forecast
$11,720,000
Variance
–$80,000

Figures illustrative · Wentworth Quarter sample data

03
Live

Dockets

The daily record of what happened on site. Labour, plant, materials, captured live, priced with contract rates, every line carrying a cost code that feeds the budget rollup.

  • Labour · plant · materials
  • Contract-aware pricing (no pyramiding, break-aware)
  • Assess & approve workflow
  • Approve, reject, return with notes
  • CSV bulk import for backlog
  • Cost codes on every line
  • Full audit trail end-to-end
  • Realtime updates across the team
app.tectm.com — Dockets
WQ

Wentworth Quarter

Aurora Property Group

6Total
3Draft
1Submitted
1Assessed
1Approved
$3,039,136Assessed Value
Search dockets…
All Statuses
All Engaged contractors
WQ-DOC-005Draft
Apex Civil Pty LtdWQ Civil Works4 × Labourers, 1 × Excavator 20t
18 Jun 2026 · 📎 3$4,200$4,200
WQ-DOC-004Draft
Apex Civil Pty LtdWQ Civil Works3 × Carpenters, formwork materials
17 Jun 2026 · 📎 2$6,800$6,800
WQ-DOC-010Draft
Atlas Structural Steel Pty LtdWQ Structural Steel2 × Ironworkers, crane hire
16 Jun 2026 · 📎 4$80,000$80,000
WQ-DOC-013Submitted
VoltPeak Electrical Pty LtdWQ Electrical Services2 × Electricians, conduit & cable
15 Jun 2026 · 📎 3$55,000$55,000
WQ-DOC-003Assessed
Apex Civil Pty LtdWQ Civil Works6 × Labourers, compactor hire
13 Jun 2026 · 📎 1$1,500$1,500
WQ-DOC-008Approved
Apex Civil Pty LtdWQ Civil Works4 × Carpenters, weekend surcharge
13 Jun 2026 · 📎 2$825$825
Showing 6 dockets1 Approved
→ feeds Claim #4
Register total$148,325
04
Live · The Tectus engine

AI contract review

Tectus mascot

Drop in a contract and the Tectus engine reads every clause on ingest. A three-pass extraction (table-of-contents map, structured fields, free-text scan) pulls the rates, retention, milestones and risk, each field cited to its source clause and page with a confidence score. The document is indexed at the same time, ready for the conversational Tectus assistant that's coming next.

  • Reads every clause on ingest
  • Cited to exact clause + page
  • Per-field confidence scores
  • Three-pass extraction (5 buckets)
  • You confirm before it applies
  • Per-project contract RAG index
  • Risk-clause extraction
  • ≈90% on our internal extraction test suite

Coming next · Tectus chat

Cited Q&A across your contracts, permission-aware; the contracts are already indexed for it.

Tectus mascot waving

Already in tectm

The rest of the spine and the evidence underneath it: what it cost, what the contract says, and the proof behind every claim.

Live

Internal rate cards

Org-scoped labour and plant rates with date-effective costs, RLS-isolated, never returned to the parties above or engaged contractors below.

Live

Cost-codes roll-up

Every docket, PO and diary line carries a cost code; cost rolls up to the budget at capture time, with a dedicated roll-up page by code.

Live

Substantiation export

On-demand PDF or zip: payment claim, substantiation, statutory dec, invoice and insurance, every line traced to source.

Live

Variations

Five line types, approval chain, audit trail.

Live

Payment certificates

Your response to a claim: what you agree to pay, locked to the claimed docket version.

Live

Date-effective rates

No pyramiding, break deduction, escalation-aware, governing principle of the data contract.

Live

Site diary

Two tracks (own-forces work and engaged-contractor dockets) each closing independently. Your record of the day.

What's bolting onto the spine next

We ship in public. The spine is live, and the instrument is growing into the full commercial cockpit. Here's the roadmap.

Forecasting & cashflow

The live number looks forward, not just back.

Soon

Resource forecast

Assign labour and plant to program activities off awarded rates, and forecast the cost.

Soon

Program-driven cashflow

Money in and money out by week, with payment lag and retention.

Soon

Cost-code pivot

Accrual and forecast columns, a company filter, an Unassigned bucket.

Procurement & materials

The cost side fills in.

Shipping now

Suppliers, catalogue & purchase orders

POs priced off the resolved rate, a downloadable PO PDF, and record-delivery.

Soon

Materials in the site diary

The four-world day: revenue, cost, labour and plant, materials, each with its own engine.

Estimating

The front of the job.

Soon

Single-sheet budget import

One Excel sheet, formulas and dropdowns wired, the total recomputed on read.

Soon

Margin-% budget entry

Scope, internal cost and margin% per line, with planned margin in dollars.

Tectus AI

The assistant comes online.

Soon

Tectus chat

Cited Q&A across your contracts. They are already indexed for it.

Soon

Tectus permissions

Fine-grained control over what the assistant can see and answer.

Shipping now

Deeper contract extraction

Labour and plant rate tabs, a payment summary, and wider document ingest.

The symmetric model completes

Up the chain as well as down.

Soon

More claim presets

BoQ, Lump Sum and Cost Plus alongside the live SOR engine.

Soon

Revenue retention, LDs & back charges

Mirror the cost model up to the client.

Soon

EOT-aware liquidated damages

LDs levied against the effective completion date, not the raw milestone.

Reporting & field

On the road, and to the board.

Soon

Portfolio & rollup reporting

Cost, claim and margin across every job; drill by trade and cost type.

Soon

Field capture & mobile

Dockets, diary and program from the ute, plus branded PDF and Excel export.

Come in on a pilot.

Book a demo and we'll walk tectm on your own contracts.